Article 1
1 On the basis of Article 32(1), (3) and (4) of Directive 2010/75/EU and of Implementing Decision 2012/115/EU, no objections are raised against the transitional national plan, which the Republic of Lithuania notified to the Commission on 31 December 2012 pursuant to Article 32(5) of Directive 2010/75/EU, as amended in accordance with the additional information sent on 26 June 2013, 20 August 2013 and 3 October 2013 .
2 The list of plants covered by the transitional national plan, the pollutants for which those plants are covered, and the applicable emission ceilings are laid down in the Annex.
3 The implementation of the transitional national plan by the Lithuanian authorities shall not exempt the Republic of Lithuania from compliance of the provisions of Directive 2010/75/EU concerning the emissions from the individual combustion plants covered by the plan, and of other relevant bodies of the European Union environmental law.
Article 2
The Commission shall assess if any subsequent changes to the transitional national plan, notified by the Republic of Lithuania in the future, comply with the provisions listed in Article 32 (1), (3) and (4) of Directive 2010/75/EU and in Implementing Decision 2012/115/EU.
Article 3
This Decision is addressed to the Republic of Lithuania.