Article 68c Unit cost for operations addressing migratory challenges resulting from the military aggression by the Russian Federation
For the implementation of operations addressing migratory challenges resulting from the military aggression by the Russian Federation, Member States may include in the expenditure declared in payment applications a unit cost linked to the basic needs and support of persons granted temporary protection or other adequate protection under national law in accordance with Council Implementing Decision (EU) 2022/382 and Council Directive 2001/55/EC . That unit cost shall be EUR 40 per week for each full week or partial week that the person is in the Member State concerned. The unit cost may be used for a maximum of 13 weeks in total, starting from the date of arrival of the person in the Union. The amounts calculated on that basis shall be regarded as public support paid to beneficiaries and as eligible expenditure for the purposes of applying this Regulation.
Article 2 Amendment to Regulation (EU) No 223/2014
Article 6a, paragraph 4, of Regulation (EU) No 223/2014 is amended as follows: (1) the following subparagraph is inserted after the first subparagraph: ‘In addition to the initial pre-financing set out in the first subparagraph, the Commission shall pay 4 % of the REACT-EU resources allocated to programmes for the year 2021 as additional initial pre-financing in 2022. For programmes in Member States which have had a level of arrivals of persons from Ukraine greater than 1 % of their national population between 24 February 2022 and 23 March 2022, that percentage shall be increased to 34 %.’; (2) the second subparagraph is replaced by the following: ‘The amount paid as initial pre-financing referred to in the first and second subparagraphs shall be totally cleared from the Commission accounts not later than when the operational programme is closed.’.
Article 3 Entry into force
This Regulation shall enter into force on the day following that of its publication in the Official Journal of the European Union.