Commission Decision (EU) 2015/1585 of 25 November 2014 on the aid scheme SA.33995 (2013/C) (ex 2013/NN) (implemented by Germany for the support of renewable electricity and of energy-intensive users) (notified under document C(2014) 8786) (Text with EEA relevance)

CELEX
32015D1585
Document type
DEC
Sector
Legislation
Date of document
2014-11-25
In force since
2015-09-25
Status
In force

Text

Article-level text, parsed from the formex manifestation.

Article 1

The State aid for the support of electricity production from renewable energy sources and from mine gas, including its financing mechanism, granted on the basis of the Erneuerbare-Energien-Gesetz 2012 (EEG-Act 2012), unlawfully put into effect by Germany in breach of Article 108(3) of the Treaty, is compatible with the internal market subject to the implementation of the commitment set out in Annex I by Germany.

Article 2

The Commission accepts the adjustment plan submitted by Germany in respect of the years 2013 and 2014, as set out in Annex II.

Article 3

1 The State aid consisting of reductions in the surcharge for the funding of support for electricity from renewable sources (EEG-surcharge) in the years 2013 and 2014 for energy-intensive users (Besondere Ausgleichsregelung, BesAR), unlawfully put into effect by Germany in breach of Article 108(3) of the Treaty, is compatible with the internal market if it falls into one of the four categories set out in this paragraph. Where the State aid was granted to an undertaking which belongs to a sector listed in Annex 3 to the Guidelines on State aid for environmental protection and energy 2014-20 (2014 Guidelines), it is compatible with the internal market if the undertaking paid at least 15 % of the additional costs faced by electricity suppliers due to obligations to buy renewable energy which are subsequently passed on to their customers. If the undertaking paid less than 15 % of those additional costs, the State aid is nevertheless compatible if the undertaking paid an amount that corresponds to at least 4 % of its gross value added or, for undertakings having an electro-intensity of at least 20 %, at least 0,5 % of gross value added. Where the State aid was granted to an undertaking which does not belong to a sector listed in Annex 3 to the 2014 Guidelines but had an electro-intensity of at least 20 % in 2012 and belonged, in that year, to a sector with a trade intensity of at least 4 % at Union level, it is compatible with the internal market if the undertaking paid at least 15 % of the additional costs faced by electricity suppliers due to obligations to buy renewable energy which were subsequently passed on to electricity consumers. If the undertaking paid less than 15 % of those additional costs, the State aid is nevertheless compatible if the undertaking paid an amount that corresponds to at least 4 % of its gross value added or, for undertakings having an electro-intensity of at least 20 %, at least 0,5 % of gross value added. Where the State aid was granted to an undertaking eligible for compatible State aid on the basis of the second or third subparagraph, but the amount of the EEG-surcharge paid by that undertaking did not reach the level required by those subparagraphs, the following parts of the aid are compatible: (a) for 2013, the part of the aid which exceeds 125 % of the surcharge that the undertaking actually paid in 2013; (b) for 2014, the part of the aid which exceeds 150 % of the surcharge that the undertaking actually paid in 2013. Where the State aid was granted to an undertaking not eligible for compatible State aid on the basis of the second or third subparagraph, and where the undertaking paid less than 20 % of the additional costs of the surcharge without reduction, the following parts of the aid are compatible: (a) for 2013, the part of the aid which exceeds 125 % of the surcharge that the undertaking actually paid in 2013; (b) for 2014, the part of the aid which exceeds 150 % of the surcharge that the undertaking actually paid in 2013.

2 Any aid that is not covered by paragraph 1 is incompatible with the internal market.

Article 4

Individual aid granted on the basis of the aid schemes referred to in Articles 1 and 3 does not constitute aid if, at the time it was granted, it fulfilled the conditions laid down by the regulation adopted pursuant to Article 2 of Council Regulation (EC) No 994/98 which was applicable at the time the aid was granted.

Article 5

Individual aid granted on the basis of the aid schemes referred to in Articles 1 and 3 which, at the time it was granted, fulfilled the conditions laid down by the regulation adopted pursuant to Article 1 of Regulation (EC) No 994/98, or by any approved aid scheme, is compatible with the internal market, up to maximum aid intensities applicable to that type of aid.

Article 6

1 Germany shall recover the incompatible aid referred to in Article 3(2) from the beneficiaries according to the method described in Annex III.

2 The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiaries until their actual recovery.

3 The interest shall be calculated on a compound basis in accordance with Chapter V of Commission Regulation (EC) No 794/2004 .

4 Germany shall cancel all outstanding payments of aid under the scheme referred to in Article 3(2) with effect from the date of adoption of this Decision.

Article 7

1 Recovery of the incompatible aid referred to in Article 3(2) shall be immediate and effective.

2 Germany shall ensure that this Decision is implemented within four months following the date of notification of this Decision by recovering the incompatible aid granted.

3 Where Germany recovers only the preliminary recovery amounts set out in paragraph 4 of Annex III, Germany shall ensure that the correction mechanism described in paragraph 4 of Annex III is implemented within one year following the date of notification of this Decision.

Article 8

1 Within two months following notification of this Decision, Germany shall submit the following information: (a) the list of beneficiaries that have received aid referred to in Article 3(1) and (2) and the total amount of aid received by each of them under the scheme; (b) the total preliminary recovery amount (principal and recovery interests) to be recovered from each beneficiary; (c) a detailed description of the measures already taken and planned to comply with this Decision, including the commitment set out in Annex I; (d) documents demonstrating that the beneficiaries have been ordered to repay the aid and that the commitment set out in Annex I is complied with.

2 Germany shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 3(2) has been completed and the commitment set out in Annex I is fully implemented. It shall immediately submit, on simple request by the Commission, information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiaries.

Article 9

Germany has committed to reinvest EUR 50 million in interconnectors and in European energy projects. Germany shall keep the Commission informed of the implementation of this commitment.

Article 10

This Decision is addressed to the Federal Republic of Germany.