2007/674/EC: Commission Decision of 4 April 2007 on State aid N 575/04 implemented by France for Ernault and measure C 32/05 (ex N 250/05), the subject of proceedings under Article 88(2) of the EC Treaty (notified under document number C(2007) 1405) (Text with EEA relevance)
Text
Article-level text, parsed from the formex manifestation.
Article 1
The state aid which was implemented by France for Ernault as rescue aid and was the subject of the Commission decision of 20 January 2005 is incompatible with the common market since it has been maintained beyond 14 December 2006.
Article 2
1 France shall take all necessary measures to recover from the beneficiary the aid referred to in Article 1 and unlawfully made available to the beneficiary.
2 Recovery shall be effected without delay and in accordance with the procedures of national law provided that they allow the immediate and effective execution of the decision. The aid to be recovered shall include interest from the date on which it was at the disposal of the beneficiary until the date of its recovery. For the period from 14 December 2006, the date on which notification of the restructuring plan was withdrawn, and the date of recovery of the aid, interest shall be calculated in accordance with the provisions of Chapter V of Commission Regulation (EC) No 794/2004 .
Article 3
The procedure provided for in Article 88(2) of the Treaty and opened by the Commission decision of 6 September 2006 (measure C 32/05) is closed as a consequence of the withdrawal of the notification of 23 May 2005.
Article 4
France shall inform the Commission, within two months of notification of this Decision, of the measures which it has already taken and plans to take to comply with Articles 1 and 2. It shall supply this information by completing the questionnaire set out in the Annex hereto.
Article 5
This Decision is addressed to the French Republic.